Link – To consolidate 10G services on ME nodes at Pietermaritzburg. +/- 6 hour break, time of break: 2026/03/19 00:01:00
Ref: NN0103916Category Planned Work Type: Planned Work Status: New
TimeDown: Thu, 19 Mar 2026 00:01:00 +0200 ETTR: 6 Hours
Areas affected: DSLAM Affected: DUNDEE MIX ISAM 03
DSLAM Affected: HAYFIELDS ISAM 01
Progress: Initial Ref logged
Link – To replace card and do software upgrade at Durban Taj Mahal. +/- 6 hour break, time of break: 2026/03/20 00:01:00
Ref: NN0103915Category Planned Work Type: Planned Work Status: New
TimeDown: Fri, 20 Mar 2026 00:01:00 +0200 ETTR: 6 Hours
Areas affected: DSLAM Affected: RAMSGATE ISAM 1
DSLAM Affected: UMDLOTI BEACH B2A4 ISAM 1
Progress: Initial Ref logged
Link – To migrate splitters from Eersterus to Eastlynne. +/- 15 hour break, time of break: 2026/03/17 09:00:00
Ref: NN0103917Category Planned Work Type: Planned Work Status: New
TimeDown: Tue, 17 Mar 2026 00:01:00 +0200 ETTR: 12 Hours
Areas affected: DSLAM Affected: EERSTERUS GPON MSAN 01
Progress: Initial Ref logged
Link – Green Co project – Divert of Splitters Tiervlei to Parow. +/- 10 hour break, time of break: 2026/03/22 22:00:00
Ref: NN0103918Category Planned Work Type: Planned Work Status: New
TimeDown: Sun, 22 Mar 2026 22:01:00 +0200 ETTR: 12 Hours
Areas affected: DSLAM Affected: TIERVLEI E12 ISAM 01
DSLAM Affected: TIERVLEI E9A6 ISAM 01
Progress: Initial Ref logged
Link – Kempton Park GPON 01 uplink upgrade to 10GIG
Ref: NN0103892Category Planned Work Type: Planned Work Status: New
TimeDown: Tue, 17 Mar 2026 00:01:00 +0200 ETTR: 5 Hours
Areas affected: DSLAM Affected: KEMPTON PARK GPON MSAN 01
DSLAM Affected: KEMPTON PARK MSAN 03
Progress: Initial Ref logged
Link – To deload of congestion on BNG’s at 5 Centenary blv. +/- 5 hour break
Ref: NN0103893Category Planned Work Type: Planned Work Status: New
TimeDown: Sun, 15 Mar 2026 00:01:00 +0200 ETTR: 5 Hours
Areas affected: DSLAM Affected: HARTENBOS GPON ISAM 05
DSLAM Affected: KROONSTAD ISAM 06
Progress: Initial Ref logged
Link – Green Co project (Network Simplification Project: Divert of Splitters [TVI] Tiervlei to Parow
Ref: NN0103890Category Planned Work Type: Planned Work Status: New
TimeDown: Mon, 16 Mar 2026 22:00:00 +0200 ETTR: 1 Hour
Areas affected: DSLAM Affected: TIERVLEI E12 ISAM 01
DSLAM Affected: TIERVLEI GPON ISAM 04
Progress: Initial Ref logged
Link – To cut over FTTH splitters from Montana to Sinoville.
Ref: NN0103889Category Planned Work Type: Planned Work Status: New
TimeDown: Thu, 12 Mar 2026 07:01:00 +0200 ETTR: 12 Hours
Areas affected: DSLAM Affected: MONTANA GPON MSAN 02
DSLAM Affected: MONTANA GPON MSAN 03
DSLAM Affected: MONTANA MSAN 1
Progress: Initial Ref logged
Link – Change BNG QOS from shared-queuing to service-queuing at Bellville
Ref: NN0103891Category Planned Work Type: Planned Work Status: New
TimeDown: Tue, 17 Mar 2026 00:01:00 +0200 ETTR: 2 Hours
Areas affected: DSLAM Affected: BRACKENFELL ISAM 08
DSLAM Affected: DURBANVILLE GOEDMOED B30A2 ISAM 2
DSLAM Affected: DURBANVILLE ISAM 14
Progress: Initial Ref logged
Link – To cut over optic cable at Dalton.
Ref: NN0103884Category Planned Work Type: Planned Work Status: New
TimeDown: Sun, 15 Mar 2026 07:01:00 +0200 ETTR: 6 Hours
Areas affected: DSLAM Affected: DALTON GPON ISAM 01
Progress: Initial Ref logged
