Blog

Link – 144F pull slack from Vault to Manhole A1 and create joint at Soshanguve. 8.30 hour break expected. Time of break 2026/10/07 08:00. day ref be issued for this work, as the area is considered unsafe to work in during the evening

Ref: NN0104440Category Planned Work Type: Planned Work Status: New
TimeDown: Wed, 07 Oct 2026 08:00:00 +0200 ETTR: 8 Hours
Areas affected: DSLAM Affected: SOSHANGUVE GPON MSAN 01
Progress: Initial Ref logged